Quick update! The inspection has gone trought with very minor recommendation. There is some gaps that need to be to be filled up or the frame need to be extended to fill the gaps.
There is one point from frame inspection in regards to extra lintel to kitchen bulkhead that Carlisle has refused to fix because they state it is as per display house. I ask them how can i confirm that unless we rip the plaster out at the display house and see the frame and still waiting on an answer.
Our lounge window is cracked (not sure why) and will need to be replaced by Carlisle. Still not sure why they need to install windows so early in the process considering it is very fragile.
Broken Window at Lounge Room |
Also, there is a broken water pipe near the planned hot water system unit that need to be replaced.
Broken Water Pipe |
Other than that, all is good, the insulation batts installation has started and the brick laying has also started.
Living Room Extra Noggins and Insulation |
Rumpus Insulation Batts |