Hi All!
It has been a while :) I have just came back from holiday and have the PCI inspection with my SS on the next day. The house has been finished and overall we are happy with the colors.
During the PCI, we had a lot of points (50+) to be fixed and rectified which most of them related to paints touch ups. However there are a lot more than that as well e.g marked windows, uneven drawer, uneven door handle, uneven power points, incorrect shower head on ensuite, incorrect switch allocation in laundry, incorrect kitchen taps (still), broken walls, etc etc...
And you think that is it? Nope... today we have a private inspection (which I am now sure that it is very important to have especially at this stage) to attend the house and he picked up another 44 points to be rectified including missing insulation bats, uneven ceiling (which is hard to fix), missing concrete tiles (which I called the SS straight away to be fixed because it is raining today), uncleaned return air (the tradies put empty bottles and woods scraps are not cleaned) etc etc...
Very disappointed with the inspection result :( but was expecting to have things that is not right at this point of time, however still not expecting it to be this much to fix. Hopefully Carlisle will be able to fully fixed and won't have to many excuses not to fix them.
Anyway now time for current photos :)
|
Front |
|
Ensuite sinks |
|
Ensuite - incorrect shower head meant to be rain head shower |
|
Ensuite - toilet |
|
Master bedroom |
|
Master bedroom |
|
Garage |
|
Lounge |
|
Living |
|
Pantry |
|
Kitchen - Still missing prespex doors and appliances |
|
Hallway |
|
Entrance |
|
Laundry |
|
Dining |
|
Rumpus |
|
Carpet meets timber |
|
Rooms hallway |
|
Bathtub |
|
Bathroom shower |
|
Bedroom |
|